May 23rd - Milling and Paving Projects Begin
The 2024 Florham Park Milling and Paving Projects are set to begin on 5/23/2024. Dates are subject to change based on work load, equipment availability, and weather.
Milling will begin on 5/23/2024 with Heritage, Rosemont, and Kenneth Court. 5/24/2024 will be Kenneth Court, Dawn Court, and Keyes Street. 5/28/2024 will be Keyes, Knapp, and Lloyd. Milling on Elm Street, Manker, Totty, and Gregmar will be 5/29/2024. Riverside will be milled on 5/30/2024.  Access to driveways will be intermittently restricted for a short term throughout the day.  Please be aware of raised manholes and utility boxes.  
Paving will begin on 5/30/2024 with Heritage, Rosemont, and Kenneth Court. 5/31/2024 will be Kenneth Court, Dawn Court, and Keyes Street. 6/3/2024 will be Keyes, Knapp, Lloyd, Elm, and Manker. Paving on Riverside, Manker, Totty, and Gregmar will be 6/4/2024.  Access to driveways and your street will be restricted 2-4 hours to allow the asphalt to compact and cure.
More: Homepage News